Here is a general update on the Woods from Jim:

  • Village Staining
    This project has been going very smooth and on budget. Happy Valley will be finishing VC # 5 on 8-19-05 and will begin VC # 6 next week. This puts us at the half way point for this project and the outlook for finishing this season is very good.

  • Village Siding
    Siding repairs are complete

  • Village Chimney
    The rebuiding part of the project was finished. We are now waiting for the installation of the new metal caps, which is set to begin on 8-18 & 8-19.

  • Cluster Door Painting
    This project will start in 2 weeks, which is good as most summer renters leave around this time.

  • Cluster Entrance Light Poles
    This project is complete. We installed a new post with cap, new sign, three light fixtures per pole and an outlet. At the base of the pole we built a 2 ft. high stone wall that is 5 ft. in diameter and filled with topsoil. Next year we will plant flowers similar to what is on the bridge.

  • Cluster Power Washing
    One building at E cluster still remains (E-1/E-2) to be done and all of D cluster needs to be done. Everything else is finished. Project should be done by the end of this week

  • Fire Ponds
    B Pond i almost done - only needs some final grading and landscaping. The A Pond digging will begin on 8-18 and will be complete by 8-24.

  • Step and Rail Repair
    We will begin more step and rail repair in the D cluster on 8-19. D has had some washouts that are effecting the stability of the steps. After D we will address the B units. After that we will step in on an as needed basis.